REPORT IN BRIEF
On August 18, 1999, the City opened bids for the City of Sunnyvale Community Center Kiln Room Addition project, PR 99/01-00. There were five bids received. Staff is recommending award of the contract for this project to the lowest responsible bidder, ICC General Contractors Inc., for the lump sum amount of $67,485.00.
BACKGROUND
There was a fire in the existing kiln room in May, 1998 which destroyed a gas kiln and a sizable portion of the roof. The investigation of the fire revealed the cause to be heat accumulation due to the excessive number of kilns in the confined area. It was, therefore, decided to move the two Gas kilns out of the existing space and into the new addition next to the existing kiln room. This project will add 421 square feet area to the kiln room.
DISCUSSION
The scope of this project is to provide a separate space for the two gas kilns by building a concrete block structure of about 421 square feet. The contract also includes landscaping, and providing of access to the new and existing kiln room.
For comparative purposes, the Engineer’s Estimate and the bids received are:
| Engineer’s Estimate | $75,000.00 |
| ICC General contractors Inc. | $67,485.00 |
|
Zolman Construction and Dev. Inc. |
$128,500.00 |
| Ranger construction Inc. | $138,104.00 |
| Jim Duffy Construction Inc. | $149,667.00 |
| A P Construction Co. Inc. | $235,000.00 |
Staff has determined that the bid from ICC General Contractors Inc. is the lowest responsible bid. It is, therefore, recommended that the contract be awarded to ICC general Contractors Inc.
A determination was made that this project will have no significant effect on the environment in accordance with CEQA guidelines for categorically exempt projects.
FISCAL IMPACT
| 1. Project Cost | |
| Construction Contract | $67,485.00 |
| Construction Contingency | $10,000.00 |
| Design Consultant (during construction) | $7,000.00 |
| Special testing and inspection | $4,000.00 |
| Owner provided Material (Hoods, etc.) | $4,500.00 |
| Total | $92,985.00 |
2. Project Budget |
|
|
|
PUBLIC CONTACT
Posting of the Council Agenda. This report is also available on the city’s internet home page and the City Library.
RECOMMENDATION
It is recommended that the City Council award the contract for subject project to the lowest responsible bidder, ICC General Contractors Inc. for the total lump sum of $67,485, and approve a construction contingency of $10,000.
Prepared by:
Hira Raina
Assistant City Engineer
Reviewed by:
Marvin A. Rose
Director of Public Works
Reviewed by:
Mary Bradley
Director of Finance
Approved by:
Robert S. LaSala
City Manager
|