RTC #99-491

November 23, 1999

 

SUBJECT: Award of Contract, Hetch-Hetchy Greenway (Morse Avenue to Borregas Avenue) Improvement Project,
PR-96/02A-99

REPORT IN BRIEF

The City opened bids for the Hetch-Hetchy Greenway (Morse Avenue to Borregas Avenue) Improvement Project (PR-96/02A-99) on October 27, 1999. There were five bids received. Staff is recommending that Council award the contract to the lowest responsible bidder, Watkin & Bortolussi, Inc., in the amount of $386,626.

BACKGROUND

The Hetch-Hetchy right-of-way is fairly linear, eighty feet wide, and extends from east to west across the entire City. It serves as a pedestrian and bicycle greenway that links Fairwood Park with Orchard Gardens Park. The construction of the portion between Calabazas Creek and Lawrence Expressway is already complete. The section of the greenway that lies between Fair Oaks Avenue and Meadow Lake Drive, and between Silverlake Drive and Lakewood Shopping Center is under construction. The next phase, which is being presented for award in this Report to Council, is located between Morse Avenue and Borregas Avenue.

Notice Inviting Bids for this phase was issued for advertisement on October 13, 1999.

DISCUSSION

The scope of work is broken into improvements included in the base bid and one additive alternate as follows:

Base Bid: Landscaping improvements and maintenance between Morse Avenue and Borregas Avenue, including demolition, clearing and grubbing, grading, drainage, planting, lighting, irrigation and fencing.

Add. Alt. #1: Construction of trellis structures.

For comparative purposes, the Engineer’s Estimate and the bids received are as follows:

Additive Alternate
Bidder Base Bid Number 1 Total
Engineer’s Estimate 400,000 50,000 450,000
Watkin & Bortolussi, Inc. 354,526 32,100 386,626
Blossom Valley Construction, Inc. 361,520 27,775 389,295
Robert A. Bothman, Inc. 363,000 40,000 403,000
RMT Landscape Contractors, Inc. 385,699 23,780 409,479
MCH Gen. Eng. Contractors, Inc. 490,000 56,500 546,500

 

Staff has reviewed the bids and determined that Watkin & Bortolussi, Inc. is the lowest responsible bidder.

A determination was made that this project will have no significant effect on the environment in accordance with CEQA guidelines. A Negative Declaration to this effect was filed with the County on April 6, 1999.

FISCAL IMPACT

1. Project Cost

Construction Contract

$386,626

Design Consultant (Remaining in Contract Plus Services During Construction)

$10,000

Construction Contingency (15%)

$58,000
TOTAL $454,626
2. Project Budget
Funds for this project are budgeted in the Hetch-Hetchy Open Space Improvement project (817550). There are sufficient funds in the project budget to cover costs.

 

PUBLIC CONTACT

Posting of the Council Agenda. This report is also available on the City’s Internet page and at the City Library.

RECOMMENDATION

That the City Council:

  1. Award the contract to the lowest responsible bidder, Watkin & Bortolussi, Inc., for the Base Bid and Additive Alternate No.1, in the amount of $386,626, and approve a construction contingency of $58,000.
  2. Approve and authorize the filing of the Notice of Determination.

 

 

 

Prepared by:

 

Mark Dettle
Assistant Director of PW/City Engineer

 

 

Reviewed by:

 

Marvin A. Rose
Director of Public Works

 

 

Reviewed by:

 

Mary Bradley
Director of Finance

 

 

Approved by:

Robert S. LaSala
City Manager