WORK PLAN FOR COUNCIL STUDY ISSUE:
"CONSIDERATION OF PARK CAPACITY AND USE ISSUES"
DEPARTMENT OF PARKS AND RECREATION
For Calendar Years 1999/2000
WORK PLAN
|
PHASE I (Calendar Year 1999) |
|
|
Draft the Work Plan |
January |
|
Study Session with Parks and Recreation Commission: Confirm Work Plan/Staff Strategy for Completing Study Issue |
01/27/99 |
|
Distribute Final Work Plan |
January |
|
Prepare Request for Consultant Proposals |
February-March |
|
Receive and Review Consultant Proposals |
February-March |
|
Interview, Select and Award Consultant |
February-March |
|
Review Sub-Element, LPM, Municipal Code, Etc. for Existing Policy Guidelines |
February-March |
|
Study Session: Parks and Recreation Commission |
03/24/99 |
|
Prepare Park Survey Instruments and Methodology |
April-May |
|
Implement Changes to Las Palmas Park on Behalf of Old Orchard Neighborhood by Spring, 1999 (See Attached Letter Dated August 31, 1998, from Director of Parks and Recreation) |
April-May |
|
Study Session: Parks and Recreation Commission |
05/12/99 |
|
Conduct Park Surveys |
June-August |
Back to RTC #00-033