ATTACHMENT B

EXHIBIT G—

PROJECT SCHEDULE OF PERFORMANCE

Land Use Entitlement- April 2000

Phasing defined- July 2000

PHASE I Plans- October 2000
Permit-  November 2000
Closing- December 2000
Construction-  January 2001
Completion-  January 2003
Hill Building Parking- November 2000* *before Phase I construction begins
Vacant Parcel Parking-  November 2000*

 

PHASE II
Plans-  January 2001
Permit- February 2001
Closing- March 2001
Construction-  April 2001
Completion- April 2003

 

PHASE III

 

Plans- April 2001
Permit-  May 2001
Closing- June 2001
Construction- July 2001
Completion-  January 2004

Public Parking Garage- with completion of Building III (Phase I or II)

Public Plaza- after completion of Public Parking Garage

Grand Surface Parking- with completion of Building III (Phase I or II)

Block 1 Surface Parking- with completion of Phase III