RTC#02-282

July 16, 2002

SUBJECT:

Acceptance of Improvements — Construction of Additional Median Left Turn Lanes on El Camino Real

RECOMMENDATION

That the City Council, by resolution, accept the project as complete and satisfactory.

DISCUSSION

The Contractor, Granite Construction Co., has satisfactorily completed Construction of Additional Median Left Turn Lanes on El Camino Real project (TR-97/07-98) within the allocated budget and for the final contract amount of $219,228.20.

The work included construction of a mid-block left-turn access between Sunnyvale Avenue and Cezanne Drive and a left-turn access between Cezanne Drive and Fair Oaks Avenue.

The work was done to reduce the large numbers of motorists making U-turns at El Camino/Cezanne and El Camino/Fair Oaks, especially during peak hours.

The project was inspected by the Public Works Project Administration Section and found to be satisfactory. Acceptance is, therefore, recommended.

Prepared by:
Hira Raina
Assistant City Engineer

Reviewed by:
Marvin A. Rose
Director of Public Works

Approved by:
Robert S. LaSala
City Manager