EXHIBIT "A-1"

IMPROVEMENTS TO ORTEGA PARK (PR-01/03-03) AND
IMPROVEMENTS TO LAKEWOOD PARK (PR-01/04-04)

PROJECT SCHEDULE

 

 

TASK

TIMELINE

 

 

 

1.

Research and Analysis

Week 1 through Week 2

2.

Submit Project Work Program

Week 2

3.

Submit preliminary Conceptual Plans

Week 4

4.

City Staff Review of preliminary Conceptual Plans

Week 4 through Week 5

5.

Submit draft Conceptual Plan

Week 7*

6.

City Staff Review of draft Conceptual Plan

Week 7 through Week 8

7.

Submit final Conceptual Plan

Week 9*

8.

City adopts final Conceptual Plan

Week 9 through Week 12

9.

Submit 30% complete Construction Plans and Specifications, including Cost Estimates

Week 15

10.

City Staff Review of 30% complete Construction Plans and Specifications

Week 15 through Week 16

11.

Submit 60% complete Construction Plans and Specifications, including Cost Estimates

Week 18

12.

City Staff Review of 60% complete Construction Plans and Specifications

Week 18 through Week 19

13.

Submit 90% complete Construction Plans and Specifications, including Cost Estimates

Week 21

14.

City Staff Review of 90% complete Construction Plans and Specifications

Week 21 through Week 22

15.

Submit final Bid Documents, including Cost Estimates

Week 23

 

 

 

 

TOTAL PROJECT TIME PERIOD

23 WEEKS

*Note: Timeline subject to change based on City’s review period