EXHIBIT "A-1"
IMPROVEMENTS TO ORTEGA PARK (PR-01/03-03) AND
IMPROVEMENTS TO LAKEWOOD PARK (PR-01/04-04)
PROJECT SCHEDULE
|
|
TASK |
TIMELINE |
|
|
|
|
|
1. |
Research and Analysis |
Week 1 through Week 2 |
|
2. |
Submit Project Work Program |
Week 2 |
|
3. |
Submit preliminary Conceptual Plans |
Week 4 |
|
4. |
City Staff Review of preliminary Conceptual Plans |
Week 4 through Week 5 |
|
5. |
Submit draft Conceptual Plan |
Week 7* |
|
6. |
City Staff Review of draft Conceptual Plan |
Week 7 through Week 8 |
|
7. |
Submit final Conceptual Plan |
Week 9* |
|
8. |
City adopts final Conceptual Plan |
Week 9 through Week 12 |
|
9. |
Submit 30% complete Construction Plans and Specifications, including Cost Estimates |
Week 15 |
|
10. |
City Staff Review of 30% complete Construction Plans and Specifications |
Week 15 through Week 16 |
|
11. |
Submit 60% complete Construction Plans and Specifications, including Cost Estimates |
Week 18 |
|
12. |
City Staff Review of 60% complete Construction Plans and Specifications |
Week 18 through Week 19 |
|
13. |
Submit 90% complete Construction Plans and Specifications, including Cost Estimates |
Week 21 |
|
14. |
City Staff Review of 90% complete Construction Plans and Specifications |
Week 21 through Week 22 |
|
15. |
Submit final Bid Documents, including Cost Estimates |
Week 23 |
|
|
|
|
|
|
TOTAL PROJECT TIME PERIOD |
23 WEEKS |
*Note: Timeline subject to change based on City’s review period