July 23, 2002

SUBJECT:

Authorization to Increase Expenditures under an Existing Contract for the Reconstruction of Curbs, Gutters, Sidewalks and Driveways (F0207-05)(RTC#02-305)

REPORT IN BRIEF

Approval is requested to increase expenditures under an existing contract with L & B Engineering, Inc., of San Francisco for the reconstruction of curbs, gutters, sidewalks and driveways for the Department of Public Works Engineering Division (ST-00//04-01).

BACKGROUND

On August 22, 2000, Council awarded a contract to L & B Engineering, the lowest responsive and responsible bidder in response to Invitation for Bids #F9906-85 for the reconstruction of curbs, gutters, sidewalks and driveways for a one-year period with an option to extend the contract for an additional year (RTC 00-298).

On October 23, 2001, Council authorized an extension of that contract for an additional year (RTC 01-370).

DISCUSSION

The contract for the reconstruction of curbs, gutters, sidewalks and driveways differs from most construction contracts in that it is impossible to exactly define the work to be done in advance of contract execution. Instead, the contract establishes pricing for a variety of related tasks with estimated quantities. Actual quantities are determined in the field. Historically, quantities have also been increased during the contract term to take advantage of CDBG funding that becomes available.

This was the first time the Purchasing Division processed this recurring contract since assuming responsibility for public works contracts in January 2000. Purchasing staff was unaware of its differences from other public works contracts and included a specific dollar amount of $563,980 in its recommendation for contract award (total of all line item extensions, based upon estimated quantities).

Public Works staff did not notice the change in handling of the contract, that resulted in an actual not-to-exceed amount being placed on the contract; and decisions affecting the type and quantity of tasks continued to be made in the field without knowledge of, nor regard to, their impact on the contract amount authorized by Council. This problem was exacerbated by the fact that $200,000 in CDBG funding became available for the construction of handicap curb ramps.

The end result is that L & B Engineering was directed to perform additional tasks, the cost of which exceeded the Council award amount by $278,171. The work has been satisfactorily completed, and the amount is now due the contractor.

Purchasing and Public Works staff have met to discuss the unique nature of this contract, and procedures have been implemented to ensure that this problem does not recur in the future on this or any other contract.

FISCAL IMPACT

Total final cost to the City for the annual reconstruction of curbs, gutters, sidewalks and driveways is $842,151.

Funds are available as follows:

215000

Roadside and Median Right-of-Way Services (Operating Funds)

$588,323

265200

Maintenance of Tennis and Basketball Courts (Operating Funds)

$3,000

312260

Water Distribution (Operating Funds)

$10,828

802650

Curb Ramps (Capital Project)

$40,000

820630

Curb Ramps (CDBG Funds)

$200,000

 

Total Contract Amount

$842,151

RECOMMENDATION

It is recommended that Council authorize additional expenditures in an amount not to exceed $278,171 under an existing contract with L & B Engineering, Inc., for the reconstruction of curbs, gutters, sidewalks and driveways, making a total contract not-to-exceed amount of $842,151.

Prepared by:
Elaine Wesely
Purchasing Officer

Reviewed by:
Mary Bradley
Director, Finance

Marvin Rose
Director, Public Works

Approved by:
Robert S. LaSala
City Manager