CITY OF SUNNYVALE
STATE OF CALIFORNIA
CONTRACT CHANGE ORDER

 

To: Top Grade Construction                                                                    Date: October 1, 2002

       50 Contractors Street

       Livermore, CA 94550 Project: ST-98/03-99                                    Change Order No. 02

You are authorized to proceed with the following work in connection with Conway Road Improvement project.

DESCRIPTION                                                                                                $AMOUNT

RFQ No. 3                                                                                                       $101,832.00

RFQ No. 4                                                                                                        $ 36,030.00

Increase scope of work to include provision of all labor, equipment, and materials to install utility substructure (conduit, vault, splice boxes) per PG&E composite drawing and specifications from PG&E, PacBell, and AT&T and sewer connection.

 

                                                                                      TOTAL ADD:            $137,862.00

 

Increase in Contract Time: 60 calendar days

This change order constitutes full and complete compensation for all labor, equipment, materials, overhead, extended overhead and profit required to perform the changes described above in accordance with the applicable provisions of the contract documents. This change order is not effective until approved by Engineer.

 

Accepted By:                  Date                          Approved By:                            Date

 

Patrick McDonald                                              Marvin A. Rose

Top Grade Construction                                    Director of Public Works