February 4, 2003
|
SUBJECT: |
Award of Bid #F0211-43 for Tasman Light Rail Pedestrian Access Improvements |
|
REPORT IN BRIEF |
|
Approval is requested for the award of a contract to Sposeto Engineering, Inc., of Union City for pedestrian access improvements to the Tasman Light Rail for the Department of Public Works Project Administration Section (Project #ST-01/03-03). |
|
BACKGROUND |
|
The scope of work for this project consists of pedestrian access improvements, including sidewalks, driveways, handicap ramps, curbs and irrigation/landscaping work around the Valley Transportation Authority (VTA) Light Rail System along Borregas, Crossman and Fair Oaks Avenues and Tasman Drive. |
|
DISCUSSION |
|
|
Bid specifications were prepared by Public Works and Purchasing staff. The Notice Inviting Bids was published in The Sun on November 20, 2002. The bid package was distributed to Bay Area Builders Exchanges and broadcast to potential contractors through the DemandStar by Onvia public procurement network. Twenty contractors requested bid documents. Sealed bids were publicly opened on December 18, 2002. Five responsive bids were received. |
|
|
Bidders |
Base Bid |
|
Engineer's Estimate |
$389,320 |
|
Sposeto Engineering, Inc., of Union City |
$362,655 |
|
George Bianchi Construction, Inc., of San Jose |
$394,879 |
|
Golden Bay Construction, Inc., of San Carlos |
$422,231 |
|
Joseph J. Albanese, Inc., of Santa Clara |
$448,381 |
|
JJR Construction, Inc., of San Mateo |
$529,793 |
|
Staff recommends acceptance of the base bid only from Sposeto Engineering, Inc., the lowest and responsible bidder. A determination was made that this project will have no significant effect on the environment in accordance with CEQA guidelines for categorically exempt projects. |
|
FISCAL IMPACT |
|
|
Project costs include: |
|
|
Construction |
$362,655 |
|
Contingency (15% of construction costs) |
$54,398 |
|
Total cost |
$417,053 |
|
Funds are available in Public Works Capital Project #821620 - Sidewalk Improvements Near Tasman Light Rail Transit. The FY 02/03 project budget is $526,647 and is funded by a TEA-21 grant ($500,000) and City gas tax monies ($26,647). |
|
|
RECOMMENDATION |
|
|
It is recommended that Council: |
|
|
1. |
Award a contract in the amount of $362,655 to Sposeto Engineering, Inc., for the Tasman Light Rail Pedestrian Access Improvements Project; and |
|
2. |
Approve a contingency in the amount of $54,398 |
|
Prepared by: |
|
Reviewed by:
Marvin Rose |
|
Approved by: Robert S. LaSala City Manager |
|
Attachments |
|
|
A. |
|
|
Previous Council Item |
Next Council Item | Corresponding Agenda |
| List of Council Meetings | List of Reports to Council | Sunnyvale Home Page |