EXHIBIT  F
Exhibit F - Impact Fees 
Cost of Recommended Improvements
  Local Intersections Total Cost
Mary/El Camino $500,000
Mary/Fremont $800,000
Mary/Evelyn $500,000
Sunnyvale/Saratoga/Remington $1,000,000
Fair Oaks/Arques $500,000
Wolfe/Kifer $1,000,000
Wolfe/Reed $500,000
Bicycle Lanes $1,050,000
Sidewalks $6,000,000
Expressway Intersections
Lawrence/Lochinvar $34,000
Lawrence/Arques Grade Separation $35,000,000.00
Total Cost $46,884,000
(less fees already collected) ($5,090,705)
Total to be Funded $41,793,295
Moffett Park Share (32%) $13,373,854
S. of 237 Share (68%) $28,419,441
Impact Fees S. of 237
Cost Per Trip Calculation Methodology
Net added P.M. Peak Hour Trips: 15,902
Fee funded: $28,419,441
Cost per trip: $1,787.16
                 
Land Use ITE Code Rate 1 Fee Unit of Measure
                 
SF Detached 210 1.01 /unit  $ 1,805.03 per dwelling unit
MF Attached 220 0.62 /unit  $ 1,108.04 per dwelling unit
Office 710 1.49 /ksf  $ 2,662.87 per 1,000 sq.ft
Retail 820 1.87 /ksf  $ 3,341.99 per 1,000 sq.ft.
Industrial 140 0.74 /ksf  $ 1,322.50 per 1,000 sq. ft.
R&D 110 0.98 /ksf  $ 1,751.42 per 1,000 sq.ft.
Hotel 310 0.61 /room  $ 1,090.17 per room
                 
                 
1 Retail rate is reduced 50 percent for pass-by.
                 
Impact Fees -- Industrial Area north of SR 237
Cost of Recommended Improvements
Mary Avenue Extension-50% share $25,000,000
Fair Share of City, Expressway Improvements - 32% $13,373,854
Total Cost, Moffett Park Improvements Share $38,373,854
                 
Cost Per Trip Calculation Methodology
Net added P.M. Peak Hour Trips: 7,466