ATTACHMENT A

 

 

WASTEWATER MANAGEMENT

 

Sanitary Sewer Collection System SDP

 

Activity

 

Product

Preventive Maintenance - Sewer Lateral Foaming

An Occasion

Preventive Maintenance - Video Inspection

100 Lineal Feet

Preventive Maintenance - Maintain Lift Stations

A Lift Station Maintained

Preventive Maintenance - Jet Flush Mains

100 Lineal Feet

Preventive Maintenance - Inspect and Clean Manholes

A  Manhole Maintained

Preventive Maintenance - Facility Maintenance

A Facility Maintained

Preventive Maintenance - Rancho Rinconada

An Occasion

Corrective Repair - Remove Lateral Plugs

A Lateral Plug Removed

Corrective Repair - Manholes

A Manhole Repaired

Corrective Repair - Cleanouts

A Cleanout Repaired

Corrective Repair - Remove Main Plugs

A Main Plug Removed

Corrective Repair -Sewer Mains

A Main Repaired

Corrective Repair - Rat and Insect Control

A Service Request Completed

Corrective Repair - Replace Laterals

A Lateral Repaired / Replaced

Corrective Repair - Fabrication

An item fabricated/repaired

Corrective Repair - Facility Maintenance

A Facility Maintained

Emergency Response - Lift Stations

An Emergency Request Completed

Emergency Response - Mains

An Emergency Request Completed

Emergency Response - Laterals

An Emergency Request Completed

Activity

Product

 

Administrative Services - Training

A Training Session Completed

Administrative Services - Management

Work Hour

Administrative Services - Support

Work Hour

Administrative Services - Utility Locates

A USA Locate Completed

Administrative Services - Standby Duty

Work Hour

 

 

Water Pollution Control Plant Operations SDP

 

Activity

 

Product

Process Solids

Lbs of Solids Removed from Process & Delivered to Digesters (in 1000 lbs.)

Process Liquids for NPDES Discharge

Million Gallons of Influent

Wastewater Processed.

Complete Preventive Operating Procedures (POP)

A Completed Work Order

Attend Training

Training Hours

Administration

Work Hours

Staff Meetings and Workplace Improvement Activities

Work Hours

Purchase Goods and Services

Products

Feed Polymer

A Gallon of Polymer

 

Water Pollution Control Maintenance SDP

 

Activity

Product

 

Complete Preventative Maintenance Work Order

Completed Work Order

Complete Major Maintenance Work Orders

Completed Work Order

Complete Modification Work Orders

Completed Work Order

Complete Corrective Maintenance Work Orders

Completed Work Order

Administration

Work Hours

Staff Meeting/Training

Work Hours

Wastewater Equipment Replacement

Dollars Allocated

 

Environmental Laboratory Services SDP

 

Activity

 

Product

Wet Chemistry Test Group I

A Test Completed

Wet Chemistry Test Group II

A Test Completed

Wet Chemistry Test Group III

A Test Completed

Solids

A Test Completed

Selective Ion Electrode Methods

A Test Completed

Titrations

A Test Completed

Metals by Atomic Absorption

A Test Completed

Specialty Metals: As, Se

A Test Completed

Metals Cold Vapor Hg

A Test Completed

Botulism Control

A Survey Completed

Acute Toxicity Testing

A Test Completed

Organic Compounds Gas Chromatography

A Sample Tested

Total Organic Carbon

A Test Completed

Activity

Product

 

Ion Chromatography

A Sample Tested

Microbiological Testing: Wastewater

A Test Completed

Wastewater Sampling

A Sample Collected

Observations/Readings

A Station Monitored

Contract Laboratory Services

Work Hours

Support Services

Work Hours

Administration - Personnel

Work Hours

Administration - Laboratory

Work Hours

Work Force Enhancement

Work Hours

 

Storm Water Collection System SDP

 

Activity

 

Product

Preventive Maintenance - Inspect and Clean Drain

Inlets by Machine

A Drain Inlet Maintained

Preventive Maintenance - Inspect and Clean Drain

Inlets by Hand

A Drain Inlet or Outfall Maintained

Preventive Maintenance - Inspect and Clean Storm

Manholes

A Storm Manhole Maintained

Preventive Maintenance - Pump Stations

A Pump Station Maintained

Preventive Maintenance - Inspections

An Inspection Completed

Corrective Repair - Replace Drain Inlet Grates

A Drain Inlet Grate Repaired

Corrective Repair - Manholes and Mains

A Manhole or Main Repaired

Corrective Repair - Pump Stations

A Pump Station Repaired

Corrective Repair - Jet Flush Sewer Mains

100 Lineal Feet

Corrective Repair - Non Permitted Connections

A Non-Permitted Connection Repaired

Emergency Response - Storm Patrol

A Storm Patrol Completed

Emergency Response - Residential Assistance

A Service Request Completed

Emergency Response - Commercial / Industrial

Assistance

A Service Request Completed

Emergency Response - Hazardous Spill Cleanup

A Hazardous Spill Contained

Administrative Services - Training

A Training Session Completed

Administrative Services - Management

Work Hours

Administrative Services - Utility Locates

A USA Locate Completed

Administrative Services - Support

Work Hours

 

By Product Reuse SDP

 

Activity

Product

 

Produce Recycled Water

Million Gallons of Water Processed during Title 22

Production

Recycled Water Used

Millions of Gallons of Recycled Water Used

Recycled Water Used in Plant

Millions of Gallons of Recycled Water Used in Plant

Biosolids Recycled

Tons of Biosolids Removed

Gas Used to Produce Energy

Cubic Feet (in thousands) of Landfill Gas Delivered to PGF

Operate Power Generation Facility (PGF)

Total Kilowatt Hours Produced (in thousands)

Complete POPS/Housekeeping Work Orders

A Completed Work Order

Maintain Power Generation Facility

A Completed Work Order

Energy Contract Management

Contract Management Hours

Electricity Sold

Kilowatt Hours Sold

Electricity Purchased

A Kilowatt Hour Purchased

Natural Gas Purchased for Electrical Production

Cu Ft Natural Gas (1000's)

Administration

Work Hours

Feed Polymer for 2 NTU Production

A Gallon of Polymer

Recycled Water Used in Plant

Million Gallons Used

Deliver Digester Gas

1000 Cubic Feet

 

Administration and Support Services SDP

 

Activity

Product

 

Administration

Work Hours

Support Services

Work Hours

Environmental Outreach

Work Hours

Intergovernmental Regulatory Program Coordination

Work Hours

Support Services Training

Work Hours

 

Pretreatment Services SDP

 

Activity

 

Product

Permitting of Significant Industrial Users (SIU)

A Permit Issued

Activity

Product

 

Commercial Facility Pretreatment Inspection

An Inspection completed

Monitoring Discharges to the Sanitary Sewer

A Sample Event Completed

Enforcement Plan Activities

Work Hours

Regulatory Program Compliance

A Report Completed

Pretreatment Program Administration

Work Hours

Urban Runofff Management Plan

An Inspection Completed

Illegal Dumping Incident Response

A Response Completed

Work Force Enhancement