Schedule for Town Center Mall Redevelopment
|
Deadline for receipt of Master Developer Proposals |
February 13, 2004 |
|
Selection of Master Developer (Redevelopment Agency) |
March 2, 2004 |
|
City Council Closed Session on negotiations |
March 2, 2004 |
|
Receipt of complete application (including underground parking option, signatures of all property owners) |
March 9, 2004 |
|
City Council Closed Session on negotiations |
March 23, 2004 |
|
Bankruptcy Disclosure Statement hearing |
April 5, 2004 |
|
Planning Commission action on General Plan Amendment, Special Development Permit, Tentative Subdivision Map, and Negative Declaration |
April 12, 2004 |
|
City Council Closed Session on negotiations |
April 20, 2004 |
|
City Council action on General Plan Amendment, Special Development Permit, Tentative Subdivision Map, and Negative Declaration |
April 27, 2004 |
|
Redevelopment Agency action on Disposition and Development Agreement and other related agreements |
April 27, 2004 |
|
Bankruptcy Confirmation Hearing on Reorganization Plan |
April 30, 2004 |
|
Close of escrow on sale of Mall to Forum |
May 15, 2004 |
|
Start of construction |
January 1, 2005 |
|
Project opening |
April 1, 2006 |