Schedule for Town Center Mall Redevelopment

 

Deadline for receipt of Master Developer Proposals

February 13, 2004

Selection of Master Developer (Redevelopment Agency)

March 2, 2004

City Council Closed Session on negotiations

March 2, 2004

Receipt of complete application (including underground parking option, signatures of all property owners)

March 9, 2004

City Council Closed Session on negotiations

March 23, 2004

Bankruptcy Disclosure Statement hearing

April 5, 2004

Planning Commission action on General Plan Amendment, Special Development Permit, Tentative Subdivision Map, and Negative Declaration

April 12, 2004

City Council Closed Session on negotiations

April 20, 2004

City Council action on General Plan Amendment, Special Development Permit, Tentative Subdivision Map, and Negative Declaration

April 27, 2004

Redevelopment Agency action on Disposition and Development Agreement and other related agreements

April 27, 2004

Bankruptcy Confirmation Hearing on Reorganization Plan

April 30, 2004

Close of escrow on sale of Mall to Forum

May 15, 2004

Start of construction

January 1, 2005

Project opening

April 1, 2006