CITY OF SUNNYVALE
City Council Study Session Summary
Equitable Adjustment to GreenTeam/Zanker Compensation Resulting from Materials Recovery Facility Construction Shutdown
February 26, 2008
The City Council met in study session at City Hall in the West Conference Room, Sunnyvale, California on February 26, 2008, with Vice Mayor Hamilton presiding.
City Councilmembers Present:
Mayor Anthony Spitaleri
Vice Mayor Melinda Hamilton
Councilmember John Howe
Councilmember Otto Lee
Councilmember Ron Swegles
Councilmember Christopher Moylan
Councilmember David Whittum
City Councilmembers Absent:
None
City Staff Present:
City Manager, Amy Chan
City Attorney, David Kahn
Assistant City Manager, Robert Walker
Director of Public Works, Marvin Rose
Assistant Director of Public Works, Mark Rogge
Solid Waste Program Manager, Mark Bowers
Visitors/Guests Present:
Todd Storti, GreenTeam/Zanker of Sunnyvale
Don Dean, GreenTeam/Zanker of Sunnyvale
Tracy Adams, GreenTeam/Zanker of Sunnyvale
Call to Order: 5:40 p.m.
Study Session Summary:
Director Rose presented an overview of the equitable adjustment to GreenTeam/Zanker compensation resulting from the SMaRT Station Materials Recovery Facility construction shutdown. Manager Bowers presented details regarding the background of the operating contract and incentives, the impact of the construction shutdown, the process by which the parties arrived at the equitable adjustment and the adjustment amount to be paid to GreenTeam/Zanker of Sunnyvale.
Councilmembers’ questions were answered by staff.
Vice Mayor Hamilton asked if there were questions or comments the public would like to present. There were none.
Adjournment: 5:55 p.m.
Debi Sargent, Solid Waste Contract Administrator
|