• Downtown Mathilda Bridge Project

Contact

HNTB Construction Manager
Andrew Kreck, P.E., C.C.M.
(408) 592-1754

City of Sunnyvale
Construction Answer Point
(408) 730-7415
TDD (408) 730-7501

RGW Construction Noise Disturbance Coordinator
(510) 377-5839

 

Downtown Mathilda Bridge Project

The Downtown Mathilda Bridge Project improves the Mathilda Avenue Bridge over Caltrain tracks and Evelyn Avenue.  The goals of the project are to:

  • Widen the bridge and approaches to provide standard lane, shoulder, and ramp widths;
  • Rebuild the off-ramp to a standard configuration, providing access to both East- and West-bound Evelyn.
  •  Improve curbs/barriers, sidewalks and pedestrian ramps to meet all accessibility requirements;
  • Eliminate the existing bridge’s “Functional Obsolete” Caltrans rating;
  • Provide new ornamental street-lighting, aesthetic bridge edge treatment, and new landscaping;
  • Provide more parking at the completion of the project;
  • Re-aligning Evelyn for proper bridge clearance, and closing Charles Avenue with a cul-de-sac;
  • Administering environmental compliance, mitigation monitoring. and grant requirements, including: Buy America, Prevailing Wage, Equal Employment Opportunity, and other obligations.
  • New intersection and traffic signals at Mathilda & California, and Mathilda Off-ramp & Evelyn;
  • Rebuilding San Andreas Court with improved pedestrian access, pavers, and landscaping.
  • Reroute underground utilities to accommodate widened bridge foundations.

Project Cost

The $25.5 million project is largely grant funded with a local agency share as follows.

Highway Bridge Rehabilitation Grant  $22,321,333 Federal Grant administered by Caltrans
Measure A  $524,000 Local Share
City gas tax or traffic mitigation   $2,708,375 Local Share
Total  $25,553,708 Includes design, construction, and  
project management

Traffic

Traffic lanes will be shifted, as necessary to keep two lanes open in each direction over the bridge.  Lane Closures are not permitted during commute hours: Northbound between 6 a.m. to 9 a.m. and Southbound between 3:30 p.m. to 6:30 p.m.

Lanes will be reopened to traffic after construction.  Construction-related vehicles are not allowed to park on neighborhood streets.  Other temporary pedestrian, bicycle and vehicle detours will be done as needed for safety.

 

Project Updates

Mathilda Bridge Update - 1/31/2012

Mathilda Bridge Update –

Recently:

The Mathilda Avenue traffic pattern has been switched to allow the construction of the median island.  ...

Read more »

Mathilda Bridge Update - 1/10/2012

Mathilda Bridge Update –

Recently:

The contractor completed concrete barriers along south-bound Mathilda Avenue. The contractor continues to...

Read more »

Mathilda Bridge Update - 11/28/2011

Recently:


The contractor continues to construct concrete barriers along South bound Mathilda Avenue. The contractor continues to install rebar reinforcement ...

Read more »

 

Project Schedule

The project began in March 2010 and is scheduled to be complete in January 2012.
 

City of Sunnyvale

Normal City Hours of Operation are
8 a.m. until 5 p.m.

(408) 730-7500

  • Sunnyvale City Hall
  • 456 W. Olive Ave.
  • Sunnyvale, CA 94086
  • TDD (408) 730-7501
  • Map and Directions 
  • City of Sunnyvale Logo
 

Can't Find It?

About the Web Site

The City of Sunnyvale Web Site
is maintained by the Sunnyvale Communications Office and
the Department of Information Technology.

Questions? Contact Us.

The Fine Print