The following closures will be in effect as indicated, weather and conditions permitting.
ARQUES AVENUE REHABILITATION PROJECT |
LOCATION |
Arques Avenue immediately west of Lawrence Expressway, and Arques Avenue between San Anselmo Way and Roosevelt Avenue |
|
what |
Preventative rehabilitation of 20 manholes on Arques Avenue and rehabilitation of the Arques Pump Station, an underground sanitary pump station |
|
When |
|
|
Date |
|
|
activity |
|
For the safety of the public and workers, traffic control measures will be used when needed. Informational and warning signs will be posted as necessary to ensure everyone’s safety. Crews will make every effort to maintain access and minimize inconvenience to motorists.