The Community Center is a popular location for events, recreation and entertainment. This year we're starting a project to update the grounds around the buildings since the site is approximately 50 years old. This will include the ponds, walkways, landscaping and open space. Our goals are to make them more attractive and easier to maintain. We also want to improve the recreational opportunities. We'll be looking for your input along the way. The first step is to determine the scope of work for the project.
Raymond Qi, Civil Engineer, 408-730-7512
We selected landscape architecture and civil engineering firm, Verde Design, Inc., as the design consultant. Together we will develop a design that meets the project goals. We will include input from community meetings and surveys.
For March 15 Community Meeting and Survey Summary and Results, see Documents tab.
Use the following opportunities to give us your feedback on the project.
Community Meeting #2
When: May 12 from 6:00 p.m. to 7:30 p.m.
Where: Register for the online meeting. Registrants will receive the link to join the meeting.
Community Meeting #3 - June
Community Survey #2 - Open May 12 to June 13
Community input will help guide the renovations. Construction options may include:
Replacement and update options may include:
Report to Council 21-0969 - October 26, 2021 - Award of Design Contract to Verde Design Inc.
Community Meeting and Survey #1 Summary and Results - March 15
Online Survey #1 Results - Feb. 1 to March 31
This project is a major renovation of the grounds surrounding the Community Center. The Center, built in 1973, is centrally located in Sunnyvale.
In 2014, Council approved a project to renovate the grounds surrounding the Community Center. The project will have a public input phase.
In October 2021, the City awarded a contract for design services to Verde Design, Inc. The design phase kicked off November 2021.